Compare cut and fill in the same state
Excavated material measured in place is called bank volume. Compacted fill occupies a different volume. Before subtracting one from the other, this calculator converts the required compacted fill back into bank volume using your stated ratio.
Measure and calculate
- Measure excavation as bank cubic feet and fill demand as compacted cubic feet.
- Enter compacted volume divided by bank volume for the specific material and process.
- Read a positive result as bank-volume surplus and a negative result as bank-volume shortfall.
Bank-volume balance = excavated bank volume − compacted fill demand ÷ compacted-to-bank ratio.
A worked example
- Inputs
- You excavate 90 bank ft³ and need 60 compacted ft³. The assumed compacted-to-bank ratio is 0.8.
- Calculation
Required bank volume: 60 ÷ 0.8 = 75 ft³. Balance: 90 − 75 = 15 bank ft³.- Result
- 15 bank ft³
The model reports a 15 bank ft³ surplus. It does not convert that surplus into loose truck volume or judge whether the excavated material is suitable for reuse.
Read the result
| Output or check | What it means for your project |
|---|---|
| Positive balance: bank ft³ | More in-place excavation is available than the bank-volume equivalent of the fill demand. Suitability for reuse remains a separate check. |
| Negative balance: bank ft³ | The magnitude is the modeled shortage in bank volume. Convert to the supplier’s delivered material state before ordering. |
| Compacted-to-bank ratio | The ratio converts between stated volumes. A bank-volume balance is not a loose-volume truckload count. |
Common questions
Does a negative answer indicate a calculation error?
Not necessarily. It means the converted fill requirement exceeds the measured excavation under your chosen ratio.
Is 0.8 a standard compaction factor?
No. It is an explicit example assumption. The usable ratio depends on the material and operation and should come from project-specific evidence.